Paragraph 4 Notifications regarding licensed activitiesI1
England and Wales
(1)
The undertaker must inform the MMO in writing—
(a)
at least 5 business days prior to the commencement of the first construction licensed activity;
(b)
within 5 business days following the completion of the final construction licensed activity, of the completion;
(c)
at least 5 business days prior to the commencement of a maintenance activity or maintenance dredging; and
(d)
within 5 business days following the completion of the maintenance activity or maintenance dredging.
Annotations
Commencement
- I1
Sch. 11 para. 4 in force at 27.11.2025, see art. 1