Paragraph 130 I1
England and Wales
Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule or in consequence of the construction, use, maintenance or failure of any part of the authorised development by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by the undertaker) in the course of carrying out such works, use or maintenance, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised development) or property of any RRRL Entity, or there is any interruption in any service provided, or in the supply of any goods, by any RRRL Entity, or any RRRL Entity becomes liable to pay any amount to any third party, the undertaker will—
bear and pay on demand the cost reasonably incurred by such RRRL Entity in making good such damage or restoring the supply; and
indemnify such RRRL Entity for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from such RRRL Entity, by reason or in consequence of any such damage or interruption or such RRRL Entity becoming liable to any third party as aforesaid other than arising from any default of such RRRL Entity.
The fact that any act or thing may have been done by a RRRL Entity on behalf of the undertaker or in accordance with a plan approved by such RRRL Entity or in accordance with any requirement of such RRRL Entity or under its supervision will not (unless sub-paragraph (3) applies), excuse the undertaker from liability under the provisions of this sub-paragraph (2) unless such RRRL Entity fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan or as otherwise agreed between the undertaker and such RRRL Entity.
Nothing in sub-paragraph (1) shall impose any liability on the undertaker in respect of—
any damage or interruption to the extent that it is attributable to the neglect or default of such RRRL Entity, its officers, servants, contractors or agents; and
any part of the authorised development and/or any other works authorised by this Part of this Schedule carried out by such RRRL Entity whether pursuant to article 9 (benefit of this Order) or as an assignee, transferee or lessee of a person with the benefit of the Order pursuant to section 156 (benefit of order granting development consent) of the Planning Act 2008 or article 10 (consent to transfer benefit of the Order) subject to the proviso that once such works become apparatus, any part of the authorised development yet to be executed and not falling within this sub-section 130(3)(b) will be subject to the full terms of this Part of this Schedule including this paragraph 130.
Each RRRL Entity must give the undertaker reasonable notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.
Each RRRL Entity must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph 130 applies. If requested to do so by the undertaker, the applicable RRRL Entity shall provide an explanation of how the claim has been minimised. The undertaker shall only be liable under this paragraph 130 for claims reasonably incurred by a RRRL Entity.
Annotations
Commencement
- I1
Sch. 12 para. 130 in force at 27.11.2025, see art. 1