Schedule 13 DOCUMENTS AND PLANS TO BE CERTIFIEDI1

England and Wales

(1)

Document name

(2)

Document reference

(3)

Revision number

(4)

Date

access and rights of way plan2.4P03September 2024
book of reference4.3Rev HMay 2025
design principles and design code5.7Rev EMarch 2025
environmental statementenvironmental statement 6.1 (excluding chapters 2, 4, 5, 7, 8, 9, 11, 14, 19, 21 and 22)Rev AMarch 2024
environmental statement 6.1 Chapter 2Rev BApril 2025
environmental statement 6.1 Chapter 4Rev BApril 2025
environmental statement 6.1 Chapter 5Rev BApril 2025
environmental statement 6.1 Chapter 7Rev BApril 2025
environmental statement 6.1 Chapter 8Rev BApril 2025
environmental statement 6.1 Chapter 9Rev BApril 2025
environmental statement 6.1 Chapter 11Rev BApril 2025
environmental statement 6.1 Chapter 14Rev BApril 2025
environmental statement 6.1 Chapter 19Rev BApril 2025
environmental statement 6.1 Chapter 21Rev BApril 2025
environmental statement 6.1 Chapter 22Rev BApril 2025
environmental statement 6.2 (excluding figures 3.3, 7.4, 7.10 and 11.2)Rev AMarch 2024
environmental statement 6.2 (figure 3.3)Rev BSeptember 2024
environmental statement 6.2 (figure 7.4)Rev BApril 2025
environmental statement 6.2 (figure 7.10)Rev BApril 2025
environmental statement 6.2 (figure 11.2)Rev BApril 2025
environmental statement 6.3 (excluding appendices 2.1, 4.2, 5.2, 5.3, 5.4, 7.8, 7.9, 10.4, 11.1, 11.2, 11.4 and 19.1)Rev AMarch 2024
environmental statement 6.3 (appendix 2.1)Rev CFebruary 2025
environmental statement 6.3 (appendix 4.2)Rev BApril 2025
environmental statement 6.3 (appendix 5.2)Rev BApril 2025
environmental statement 6.3 (appendix 5.3)Rev BApril 2025
environmental statement 6.3 (appendix 5.4)Rev BApril 2025
environmental statement 6.3 (appendix 7.8)Rev BApril 2025
environmental statement 6.3 (appendix 7.9)Rev BApril 2025
environmental statement 6.3 (appendix 11.1)Rev BApril 2025
environmental statement 6.3 (appendix 11.2)Rev BSeptember 2024
environmental statement 6.3 (appendix 11.4)Rev BApril 2025
environmental statement 6.3 (appendix 19.1)Rev EApril 2025
environmental statement 6.3 (appendix 10.4)Rev BJanuary 2025
extended crossness local nature reserve plan2.9P04January 2025
flood risk assessment6.3 Appendix 11.2Rev BSeptember 2024
framework construction traffic management plan7.7Rev EMarch 2025
land plans2.2P05February 2025
mitigation schedule7.8Rev BNovember 2024
outline landscape, biodiversity, access and recreation delivery strategy7.9Rev HOctober 2025
outline code of construction practice7.4Rev EMarch 2025
outline drainage strategy7.2Rev CApril 2025
outline emergency preparedness and response plan7.11Rev CApril 2025
outline lighting strategy7.3Rev BMarch 2025
outline site waste management plan7.10Rev BApril 2025
outline skills and employment plan9.15Rev ADecember 2024
preliminary navigation risk assessment6.3 Appendix 19.1Rev EApril 2025
traffic regulation measures plan2.6P03September 2024
works plans2.3P08April 2025

Annotations

Commencement

I1

Sch. 13 in force at 27.11.2025, see art. 1