Schedule 16 DESIGN PARAMETERSI1
England and Wales
| (1) Component/Building/Area | (2) Works Area | (3) Maximum Number | (4) Maximum Height (m) of Component/ Building/ Area | (5) Maximum Height (m) | (6) Further Parameters |
|---|---|---|---|---|---|
| Direct Contact Cooler | 1A | 2 | 30 | 33 Above Ordnance Datum | - |
| Absorber Column(s) and Stack(s) | 1B | 2 combined Absorber Columns and Stacks or a maximum of 2 Absorber Columns and 2 Stacks | 110 | 113 Above Ordnance Datum | Minimum vertical distance between top of Absorber Column(s) and top of Stack(s) whether combined or separate – 30m Minimum height of the top of Stack(s) – 100m from development platform as built Where there are 2 Stacks: Maximum internal diameter of Stack associated with Riverside 1: 3.1m Maximum internal diameter of Stack associated with Riverside 2: 2.5m Where there is 1 Stack: Maximum internal diameter of Stack: 4.0m |
| Regenerator | 1A | 2 | 60 | 63 Above Ordnance Datum | - |
| Compression Plant | 1C | 2 | 45 | 48 Above Ordnance Datum | - |
| CO2 Dehydration | 1C | 2 | 25 | 28 Above Ordnance Datum | - |
| CO2 Liquefaction | 1C | 2 | 30 | 33 Above Ordnance Datum | - |
| CO2 Vents | 1C | 2 | 45 | 48 Above Ordnance Datum | - |
| LCO₂ Buffer Storage Area | 1D | 16 | 45 | 48 Above Ordnance Datum | - |
| Hybrid or Dry Cooling Tower | 1E | 2 | 32 | 35 Above Ordnance Datum | - |
| Water Treatment Plant and Wastewater Treatment Plant | 1E | 2 | 20 | 23 Above Ordnance Datum | - |
| Back Pressure Turbine and Generator | 1A | 2 | 35 | 38 Above Ordnance Datum | - |
| Insulated heat pipework and flue gas ducting | 2A(ii) and 2b(i) | - | 30 | 33 Above Ordnance Datum | - |
| Loading platform (not including topside infrastructure and equipment) | 4C | 1 | - | 11.5 Above Chart Datum | Maximum length of 40 metres Maximum width of 50 metres |
| Breasting Dolphins | 4B | 4 | - | 11.5 Above Chart Datum | - |
| Mooring Dolphins | 4B | 6 | - | 11.5 Above Chart Datum | Maximum length of 7 metres Maximum width of 7 metres |
| Access Trestle Start Point (not including topside infrastructure and equipment) | 4B | 1 | - | 20 Above Ordnance Datum | Maximum length of 335 metres Maximum width of 10 metres |
| LCO2 pipelines, piperacks and pipe bridges | 5 | - | 30 | 33 Above Ordnance Datum | - |
Annotations
Commencement
- I1
Sch. 16 in force at 27.11.2025, see art. 1