Paragraph 10 Emergency preparedness and response planI1
England and Wales
Work Nos. 1 and 4 must not be fully commissioned until an emergency preparedness and response plan has been submitted to and approved by the relevant planning authority in writing, in consultation with the Environment Agency, lead local flood authority, the London Fire Brigade and, in respect of Work No. 4 only, the PLA.
For the purposes of sub-paragraph (1), the undertaker may submit one emergency preparedness and response plan for both Work Nos. 1 and 4 or one for each of Work No. 1 and Work No. 4.
The emergency preparedness and response plan must be implemented as approved under sub-paragraph (1) and maintained throughout the operation of the relevant part of Work Nos. 1 or 4 to which the plan or plans relate.