Paragraph 25 Heat StrategyI1
England and Wales
No part of the authorised development may be commenced until the undertaker has submitted a heat strategy to the relevant planning authority for its written approval.
The heat strategy submitted under sub-paragraph (1) must—
provide an explanation of how the heat to be produced as a result of the authorised development, Riverside 1 and Riverside 2 could be captured and exported off-site;
set out the appropriate infrastructure that could be brought forward within the Order limits to enable the capture and export of heat from the site;
identify potential connection points for export of heat produced as a result of the authorised development, Riverside 1 and Riverside 2; and
provide an update on discussions with potential heat network providers.
The heat strategy submitted, and the relevant planning authority approval under sub-paragraph (1) must not require the undertaker to repeat actions already undertaken pursuant to—
requirement 24 (combined heat and power) of the REP Order;
any document produced pursuant to requirement 24 of the REP Order;
condition 31 of planning permission 16/02167/FUL relating to Riverside 1 issued by the London Borough of Bexley;
condition 31 of the consent issued under section 36C of the Electricity Act 1989 in respect of Riverside 1 dated 17 December 2021;
any condition of planning permission 22/00728/FUL issued by the London Borough of Bexley; and
Annotations
Commencement
- I1
Sch. 2 para. 25 in force at 27.11.2025, see art. 1