Paragraph 1 InterpretationI1
England and Wales
In this Schedule—
“relevant planning authority”, unless as provided otherwise, means—
- (a)
- (b)
West Lindsey District Council and Bassetlaw District Council for the purposes of—
- (i)
Requirement 3 (approved details and amendments to them);
- (ii)
Requirement 4 (community liaison group);
- (iii)
Requirement 5 (detailed design approval);
- (iv)
Requirement 7 (landscape and ecological management plan);
- (v)
Requirement 8 (ecological protection and mitigation strategy);
- (vi)
Requirement 9 (biodiversity net gain);
- (vii)
Requirement 10 (fencing and other means of enclosure);
- (viii)
Requirement 13 (construction environmental management plan);
- (ix)
Requirement 14 (operational environmental management plan);
- (x)
Requirement 16 (operational noise);
- (xi)
Requirement 20 (skills, supply chain and employment);
- (xii)
Requirement 21 (decommissioning and restoration);
- (i)
- (c)
F1Nottinghamshire County Council and Lincolnshire County Council for Requirement 12 (archaeology);
- (d)
Lincolnshire County CouncilF2... for Requirement 22 (long term flood risk mitigation).
“relevant highway authority” means the highway authority for the highways that are the subject of a construction traffic management plan submitted pursuant to requirement 15(3).
Annotations
Textual amendments
- F1
Words in Sch. 2 para. 1 substituted (26.11.2024) by The Cottam Solar Project (Correction) Order 2024 (S.I. 2024/1222), art. 1, Sch.
- F2
Words in Sch. 2 para. 1 omitted (26.11.2024) by virtue of The Cottam Solar Project (Correction) Order 2024 (S.I. 2024/1222), art. 1, Sch.
Commencement
- I1
Sch. 2 para. 1 in force at 27.9.2024, see art. 1