Paragraph 28 EU ETS installationsF1

(F21)

Subject to sub-paragraph (2), A is not supplied with electricity or gas to the extent that supply is consumed by A—

(a)

before IP completion day for the purposes of operating an EU ETS installation; or

(b)

on or after IP completion day in circumstances which, had that supply been consumed before IP completion day, would have been treated as being for the purposes of operating an EU ETS installation.

(2)

A is supplied with electricity or gas where A decides that such a supply is not consumed for the purposes of operating an EU ETS installation.

(3)

A decision made under sub-paragraph (2)—

(a)

may be made in respect of a phase where such a decision is made on or before the participant submits its first annual report for that phase;

(b)

must not be altered during the phase.

Annotations

Textual amendments

F1

Order revoked (with savings) (1.10.2018) by The CRC Energy Efficiency Scheme (Revocation and Savings) Order 2018 (S.I. 2018/841), arts. 1, 3

F2

Sch. 1 para. 28(1) substituted (31.12.2020) by The CRC Energy Efficiency Scheme (Amendment) (EU Exit) Regulations 2018 (S.I. 2018/1336), regs. 1, 2(2)(b) (as amended by S.I. 2020/711, regs. 1(2), 3(2)(b)); 2020 c. 1, Sch. 5 para. 1(1)