Paragraph 29 CCA facility consumptionF1
Subject to sub-paragraph (2), A is not supplied with electricity or gas to the extent that supply is consumed by A for the purposes of operating a CCA facility specified in a current specified facility certificate.
A is supplied with electricity or gas where A decides that such a supply is not consumed for the purposes of operating a CCA facility specified in a specified facility certificate.
A decision made under sub-paragraph (2)—
may be made in respect of a phase where such a decision is made on or before the participant submits its first annual report for that phase;
must not be altered during the phase.
For the purposes of the initial phase, A is not supplied with electricity or gas to the extent that it is consumed by A for the purposes of operating a CCA facility that is subject to a CCA target that ends no earlier than 2 months before the beginning of that phase.
Annotations
Textual amendments
- F1
Order revoked (with savings) (1.10.2018) by The CRC Energy Efficiency Scheme (Revocation and Savings) Order 2018 (S.I. 2018/841), arts. 1, 3