Paragraph 29A Metallurgical and mineralogical processes consumptionF1F2
Subject to sub-paragraph (2), A is not supplied with electricity or gas to the extent that that supply is consumed by A for the purposes of operating a metallurgical process or a mineralogical process.
A is supplied with electricity or gas where A decides that such a supply is not consumed for the purposes of operating a metallurgical process or a mineralogical process.
A decision made under sub-paragraph (2)—
may be made in respect of a phase where such a decision is made on or before the date the participant submits its first annual report for that phase; and
must not be altered during that phase.
“Metallurgical process” means—
any process falling within—
Division 24 of NACE Rev 2, except a process falling within Group 24.46; or
Group 25.5 of NACE Rev 2, except a process involving sheet metal; or
the following processes falling within Group 25.6 of NACE Rev 2—
plating, anodising, or other similar processing of metals;
heat treatment of metals; or
where carried out in conjunction with a process falling within paragraph (a), deburring, sandblasting, tumbling or cleaning of metals.
In sub-paragraph (4), “NACE Rev 2” F3as it applied immediately before IP completion day has the same meaning as it has in Article 1(1) of Regulation (EC) No 1893/2006 of the European Parliament and of the Council establishing the statistical classification of economic activities NACE Revision 2 and a reference to “Division” and “Group” is to those matters as set out in Annex 1 to the Regulation.
“Mineralogical process” has the same meaning as it has in Article 2(4)(b) of Council Directive 2003/96/EC restructuring the Community framework for the taxation of energy products and electricity.
Annotations
Textual amendments
- F1
Order revoked (with savings) (1.10.2018) by The CRC Energy Efficiency Scheme (Revocation and Savings) Order 2018 (S.I. 2018/841), arts. 1, 3
- F2
Sch. 1 para. 29A inserted (1.4.2014) by The CRC Energy Efficiency Scheme (Amendment) Order 2014 (S.I. 2014/502), arts. 1(1), 6(7)
- F3
Words in Sch. 1 para. 29A(5) inserted (31.12.2020) by The CRC Energy Efficiency Scheme (Amendment) (EU Exit) Regulations 2018 (S.I. 2018/1336), regs. 1, 2(2)(c) (as amended by S.I. 2020/711, regs. 1(2), 3(2)(c)); 2020 c. 1, Sch. 5 para. 1(1)