The Daventry International Rail Freight Interchange Alteration Order 2014
S.I. 2014/1796 · Made 3 July 2014 · Extends to England, Wales and Scotland
Infrastructure Planning
Made 3rd July 2014
Coming into force 24th July 2014
The application was examined in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 2010f3, by a single appointed person appointed by the Secretary of State in accordance with Chapter 3 of Part 6 of the 2008 Act.
The single appointed person, having considered the representations made and not withdrawn and the application together with accompanying documents, in accordance with section 83 of the 2008 Act, has submitted a report to the Secretary of State.
The Secretary of State, having considered the representations made and not withdrawn, and the report of the single appointed person, has decided to make an Order granting development consent for the development described in the application with modifications which in the opinion of the Secretary of State do not make any substantial change to the proposals comprised in the application.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 122 of, and paragraphs 1 to 3, 10 to 18, 33, 34, 36 and 37 of Part 1 of Schedule 5 to, the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
S.I. 2009/2264, amended by S.I. 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522 and S.I. 2013/755.
- f2
-
2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20).
- f3
-
S.I. 2010/103, amended by S.I. 2012/635.
Contents
- Part 1: Preliminary
- 1Citation and commencement
- 2Interpretation
- Part 2: Principal powers
- 3Development consent granted by the Order
- 4Parameters of authorised development
- 5Authorisation of use
- 6Maintenance of authorised development
- 7Benefit of Order
- 8Application and modification of legislative provisions
- 9Defence to proceedings in respect of statutory nuisance
- Part 3: Streets
- 10Power to alter layout, etc., of streets
- 11Street works
- 12Stopping up of streets
- 13Public rights of way – diversion and stopping up
- 14Temporary stopping up of streets
- 15Access
- 16Agreements with highway authorities
- Part 4: Supplemental powers
- 17Discharge of water
- 18Authority to survey and investigate the land
- Part 5: Powers of acquisition
- 19Compulsory acquisition of rights
- 20Time limit for exercise of authority to acquire rights compulsorily
- 21Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- 22Rights under or over streets
- 23Apparatus and rights of statutory undertakers in stopped up streets
- Part 6: Miscellaneous and general
- 24Operation and use of railways
- 25Charges
- 26Felling or lopping of trees
- 27Protection of interests
- 28Certification of plans etc.
- 29Service of notices
- 30Arbitration
- Signature
- Schedule 1: AUTHORISED DEVELOPMENT
- 1ALTERATION OF THE EXISTING DAVENTRY INTERNATIONAL RAIL FREIGHT INTERCHANGE
- 2ASSOCIATED DEVELOPMENT
- Schedule 2: REQUIREMENTS
- 1Interpretation
- 2Time Limit
- 3Phases of development
- 4Design and phasing of access and highways works
- 5Design and phasing of access and highways works
- 6Detailed design approval
- 7Detailed design approval
- 8Provision of Landscaping
- 9Implementation and maintenance of landscaping
- 10Ecological Management Plan
- 11M1 boundary slopes
- 12Fencing and other means of enclosure
- 13Construction Environmental Management Plan
- 14Earthworks
- 15Archaeology
- 16Lighting Details
- 17Building Sustainability
- 18Lorry Park
- 19Flood Risk and Surface Water Drainage
- 20Flood Risk and Surface Water Drainage
- 21Flood Risk and Surface Water Drainage
- 22Flood Risk and Surface Water Drainage
- 23Flood Risk and Surface Water Drainage
- 24Flood Risk and Surface Water Drainage
- 25Flood Risk and Surface Water Drainage
- 26Foul Water Drainage
- 27Construction Hours
- 28Construction Noise
- 29Construction Vibration
- 30Noise during the Operational Phase
- 31Monitoring of Complaints
- 32Contamination Risk
- 33Contamination Risk
- Schedule 3STREETS SUBJECT TO STREET WORKS
- Schedule 4: STREETS TO BE PERMANENTLY STOPPED UP
- 1STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
- 2STREETS FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED
- Schedule 5: PUBLIC RIGHTS OF WAY TO BE STOPPED UP
- 1PUBLIC RIGHTS OF WAY TO BE PERMANENTLY STOPPED UP
- 2PUBLIC RIGHTS OF WAY TO BE TEMPORARILY STOPPED UP
- Schedule 6: PROTECTIVE PROVISIONS
- 1Application
- 2Interpretation
- 3Acquisition of land
- 4Removal of apparatus
- 5Facilities and rights for alternative apparatus
- 6Retained apparatus
- 7Expenses
- 8Indemnity
- 9Ground subsidence monitoring scheme in respect of National Grid’s apparatus
- 10Enactments and agreements
- 11Co-operation
- 12Access
- 13Arbitration
- Explanatory note