Paragraph 12 Layout rulesI1
England, Wales and Scotland
(1)
The positions of wind turbine generators and offshore platforms must be arrayed in accordance with the parameters applicable to Work No. 1B specified in the Conditions and the principles in section 5.2 of Chapter 5 of the environmental statement.
(2)
The construction of wind turbine generators or offshore platforms must not commence until the array location and layout plan has been agreed.
(3)
The construction of wind turbine generators and offshore platforms must be carried out in accordance with the array location and layout plan.