Paragraph 17 Pre-construction plans and documentationI1

England, Wales and Scotland

(1)

Each programme, statement, plan, protocol, scheme or details required to be approved under Condition 16 must be submitted for approval at least 4 months before the intended commencement of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.

(2)

The licensed activities must be carried out in accordance with the programmes, statements, plans, protocols, schemes and details approved under Condition 16.

Annotations

Commencement

I1

Sch. 9 para. 17 in force at 26.8.2015, see art. 1