Paragraph 4 Notice of start of commissioning and notice of date of full commissioningI1
England and Wales
Notice of the intended start of commissioning of each of numbered works 1A and 2A must be given to the relevant planning authority prior to such start and in any event within seven days from the date that commissioning is started.
Within seven days of the completion of the commissioning of numbered work 1A, the undertaker must provide the relevant planning authority with notice of the date upon which such commissioning was duly completed.
Within seven days of the completion of the commissioning of numbered work 2A, the undertaker must provide the relevant planning authority with notice of the date upon which such commissioning was duly completed.
Annotations
Commencement
- I1
Sch. 2 para. 4 in force at 25.10.2019, see art. 1