Schedule 2 REQUIREMENTS
England and Wales
- 1Interpretation
- 2Commencement of the authorised development
- 3Phasing of the authorised development
- 4Notice of start of commissioning and notice of date of full commissioning
- 5Requirement for written approval
- 6Approved details and amendments to them
- 7Detailed design approval
- 8Provision of landscape and biodiversity mitigation
- 9Public rights of way diversions
- 10External lighting during construction and operation
- 11Highway accesses and passing place during construction
- 12Means of enclosure
- 13Surface water drainage
- 14Flood risk mitigation
- 15Ground conditions
- 16Archaeology
- 17Construction environmental management plan
- 18Construction traffic management plan
- 19Construction worker travel plan
- 20Construction hours
- 21Control of noise: operation
- 22Carbon capture readiness reserve space
- 23Carbon capture readiness monitoring report
- 24Air safety
- 25Local liaison committee
- 26Decommissioning environmental management plan
- 27Decommissioning traffic management plan
- 28Combined heat and power