Paragraph 15 Fencing and other means of enclosureI1
England, Wales and Scotland
No stage of the connection works shall be commenced until for that stage written details of all proposed permanent and temporary fences, walls or other means of enclosure of the connection works have been submitted to and approved by the relevant planning authority.
All construction consolidation sites must remain securely fenced in accordance with the approved details at all times during construction of the relevant stage of the connection works.
Any temporary fencing must be removed on completion of the relevant stage of the connection works.
Any approved permanent fencing in relation to Work No. 39 must be completed before the relevant work is brought into use and maintained for the operational lifetime of Work No. 39.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 15 in force at 7.7.2014, see art. 1