Paragraph 23 Construction hoursI1

England, Wales and Scotland

(1)

Construction work for the connection works and any construction-related traffic movements to or from the site of the connection works shall not take place other than between 0700 hours and 1900 hours Monday to Saturday, with no activity on Sundays or bank holidays, save—

(a)

where continuous periods of operation are required as assessed in the environmental statement, such as concrete pouring and directional drilling (subject to sub-paragraphs (3) and (4));

(b)

for internal fitting out works associated with the onshore converter station comprised within Work No. 39;

(c)

for the delivery of abnormal loads to the connection works, which may cause congestion on the local road network; and

(d)

where connection works are being carried out on the foreshore.

(2)

All construction operations which are to be undertaken outside the hours specified in sub-paragraph (1) must be agreed with the relevant planning authority in writing in advance, and must be carried out within the agreed times.

(3)

Construction of Work No. 21 shall not take place other than between 0700 hours and 1900 hours Monday to Saturday, with no activity on Sunday or bank holidays.

(4)

Construction of Work No. 26 shall not take place other than between 0700 hours and 1900 hours Monday to Friday and 0700 hours and 1400 hours on Saturday, with no activity on Sunday or bank holidays.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 23 in force at 7.7.2014, see art. 1