No meteorological mast, wind turbine generator or offshore substation forming part of the authorised project shall be erected within the areas hatched black on the works plan, whose coordinates are specified below and more particularly shown on the Order limits boundary coordinates plan—

Coordinates for restricted build area

PointLatitude (DMS)Longitude (DMS)
i52° 17′ 29.501″2° 21′ 18.183″
ii52° 19′ 32.953″2° 29′ 16.557″
iii52° 19′ 47.657″2° 34′ 8.460″
iv52° 20′ 36.356″2° 34′ 8.509″
v52° 20′ 18.296″2° 28′ 48.188″
vi52° 23′ 17.520″2° 31′ 41.224″
vii52° 21′ 52.244″2° 34′ 8.586″
viii52° 18′ 15.948″2° 34′ 8.368″
ix52° 7′ 15.824″2° 32′ 52.848″
x52° 4′ 49.734″2° 30′ 59.349″
xi52° 4′ 48.985″2° 28′ 5.706″