Paragraph 7A As built offshore parametersF1

(1)

After 25 December 2021—

(a)

no works under Works No.1, 2 or 3A may be carried out in reliance on this Order, other than works which do not give rise to any materially new or materially different environmental effects to those which would arise from the development in accordance with the parameters set out in Works No. 1, 2 and 3A and Requirements 3 to 7; and

(b)

the parameters set out in Works No. 1, 2 and 3A and Requirements 3 to 7 will be treated as the maximum defined parameters for the purposes of any application under Schedule 6 to the Planning Act 2008.

(2)

This requirement shall take precedence over any other provision in this Order.

(3)

For the purpose of this requirement “maximum defined parameters” means the defined parameters set for the purposes of considering the worst case impacts of the development in preparing the environmental statement and carrying out the Secretary of State’s Habitats Regulations Assessment (the Rochdale Envelope).

Annotations

Textual amendments

F1

Sch. 1 Pt. 3 para. 7A inserted (25.9.2021) by The East Anglia ONE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/1086), arts. 1, 5(f)