Paragraph 8 Retained apparatus: protection: electricity undertakersI1
England, Wales and Scotland
Not less than 56 days before commencing the execution of any works authorised by this Order that are near to, or will or may affect, any apparatus the removal of which has not been required by the undertakers under paragraph 5(2) or otherwise, the undertakers shall submit to the statutory undertakers in question a plan.
In relation to works which will or may be situated on, over, under or within 8.1 metres measured in any direction of any apparatus, or involve embankment works within 8.1 metres of any apparatus, the plan to be submitted to the statutory undertakers under sub-paragraph (1) shall be detailed including a material statement and describing—
the exact position of the works;
the level at which these are proposed to be constructed or renewed;
the manner of their construction or renewal including details of excavation, positioning of plant;
the position of all apparatus; and
by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus.
The undertakers shall not commence the construction or renewal of any works to which sub-paragraph (1) or (2) applies until the statutory undertakers has given written approval of the plan so submitted.
Any approval of the statutory undertakers required under sub-paragraph (3)—
may be given subject to reasonable conditions for any purpose mentioned in sub-paragraph (5) or (7);
shall not be unreasonably withheld.
In relation to a work to which sub-paragraph (1) or (2) applies, the statutory undertakers may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its system against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus provided that such modifications are made within a period of 56 days beginning with the date on which the plan under sub-paragraph (1) is submitted to it. For the avoidance of doubt, provided that any further iterations of the plan submitted to the statutory undertakers for approval as a result of modifications required under this paragraph are not materially different to the modifications previously made by the statutory undertakers, any further required modifications will be made by the statutory undertakers as soon as reasonably practicable thereafter and in any event within 21 days of receipt of any further plans.
Works executed under this Order shall be executed only in accordance with the plan, submitted under sub-paragraph (1) or as relevant sub paragraph (2), as amended from time to time by agreement between the undertakers and the statutory undertakers and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (5) or (7) by the statutory undertakers for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the statutory undertakers shall be entitled to watch and inspect the execution of those works.
Where statutory undertakers require any protective works to be carried out either themselves or by the undertakers (whether of a temporary or permanent nature) such protective works shall be carried out to the statutory undertakers’ satisfaction prior to the carrying out of any works authorised by the Order (or any relevant part thereof) and the statutory undertakers shall give 56 days’ notice of such works from the date of submission of a plan in line with sub-paragraph (1) or (2) (except in an emergency).
If a statutory undertakers in accordance with sub-paragraph (5) or (7) and in consequence of the works proposed by the undertakers, reasonably requires the removal of any apparatus and gives written notice to the undertakers of that requirement, paragraphs 1 to 3 and 6 to 8 shall apply as if the removal of the apparatus had been required by the undertakers under paragraph 5(2).
Nothing in this paragraph shall preclude the undertakers from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of any works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph shall apply to and in respect of the new plan.
The undertakers shall not be required to comply with sub-paragraph (1) where it needs to carry out emergency works as defined in the 1991 Act but in that case it shall give to the statutory undertakers in question notice as soon as is reasonably practicable and a plan of those works and shall—
comply with sub-paragraphs (5), (6) and (7) insofar as is reasonably practicable in the circumstances; and
comply with sub-paragraph (11) at all times.
At all times when carrying out any works authorised under the Order comply with National Grid’s policies for development near over headlines EN43-8 and HSE’s guidance note 6 “Avoidance of Danger from Overhead Lines”.