Paragraph 17 Fencing and other means of enclosureI1

England, Wales and Scotland

(1)

No stage of the connection works may commence until for that stage written details of all proposed permanent and temporary fences, walls or other means of enclosure of the connection works have been submitted to and approved by the relevant planning authority.

(2)

All construction consolidation sites must remain securely fenced in accordance with the approved details at all times during construction of the relevant stage of the connection works.

(3)

Any temporary fencing must be removed on completion of the relevant stage of the connection works.

(4)

Any approved permanent fencing in relation to an onshore substation must be completed before that onshore substation is brought into use and maintained for the operational lifetime of the onshore substation.