Paragraph 18 Surface and foul water drainageI1
England, Wales and Scotland
No stage of the connection works may commence until for that stage written details of the surface and (if any) foul water drainage system (including means of pollution control) have, after consultation with the relevant drainage authorities, Suffolk County Council and the Environment Agency, been submitted to and approved by the relevant planning authority.
The details agreed in paragraph (1) must accord with the proposals for a surface water and drainage management plan contained in the outline code of construction practice and include a surface water drainage scheme for Work No. 67, which is based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the development.
The surface and foul water drainage system for the relevant stage must be constructed in accordance with the approved details.