Paragraph 29 European protected species onshoreI1
England, Wales and Scotland
No stage of the connection works may commence until final pre-construction survey work has been carried out to establish whether a European protected species is present on any of the land affected, or likely to be affected, by that stage of the connection works or in any of the trees to be lopped or felled as part of that stage of the connection works.
Where a European protected species is shown to be present, the relevant part(s) of the connection works must not begin until, after consultation with Natural England and the relevant planning authority, a scheme of protection and mitigation measures has been submitted to and approved by the relevant planning authority. The connection works must be carried out in accordance with the approved scheme.
“European protected species” has the same meaning as in regulations 40 and 44 of the Conservation of Habitats and Species Regulations 2010f1.