Paragraph 30 Restoration of land used temporarily for constructionI1
England, Wales and Scotland
Any land landward of mean low water within the Order limits which is used temporarily for construction of the connection works and not ultimately incorporated in permanent works or approved landscaping, must be reinstated in accordance F1with such details as the relevant planning authority in consultation with the relevant highway authority may approve, as soon as reasonably practicable and in any event within twelve months of completion of the relevant stage of the connection works, save that if approved by the relevant planning authority Work No. 65 may be retained between any phases of construction works for Work No.67.
Annotations
Textual amendments
- F1
Words in Sch. 1 Pt. 3 para. 30 substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
Commencement
- I1
Sch. 1 Pt. 3 para. 30 in force at 29.8.2017, see art. 1