England, Wales and Scotland
F1The total number of offshore electrical stations forming part of the authorised project must not exceed one, the total number of accommodation platforms must not exceed one and the total number of meteorological masts must not exceed two.
The dimensions of any F2offshore electrical station forming part of the authorised project (excluding towers, helipads, masts and cranes) must not exceed 70 metres in height when measured from LAT, 80 metres in length and 120 metres in width.
The dimensions of any accommodation platform forming part of the authorised project must not exceed 60 metres in height when measured from LAT, 70 metres in length and 70 metres in width.
Each meteorological mast must not exceed a height of 160 metres above LAT.
Each meteorological mast must not have more than one supporting foundation.
The dimensions of any buoy forming part of the authorised project must not exceed 6 metres in height (excluding any apparatus or equipment fixed to the buoy), 4 metres in length and 4 metres in width and the anchor footprint must not exceed 4m².
Offshore platforms forming part of the authorised project must not be erected within the platform exclusion zone, whose co-ordinates are specified below—
| Point | Latitude (DMS) | Longitude (DMS) | Point | Latitude (DMS) | Longitude (DMS) |
|---|---|---|---|---|---|
| 1 | 52° 30′ 20.0268″N | 2° 48′ 33.264″E | 3 | 52° 32′ 10.4568″N | 2° 45′ 31.9572″E |
| 2 | 52° 31′ 32.0664″N | 2° 45 ′ 31.8672″E | 4 | 52° 30′ 48.7369″N | 2° 48′ 57.7512″E |
In the case of two offshore phases, taken together the combined offshore phases must not exceed—
up to one accommodation platform;
up to two meteorological masts;
up to 12 buoys fixed to the sea bed; and
F7up to one offshore electrical station.
The total number of gravity base foundations must not exceed 100.
Annotations
Textual amendments
- F1
Words in Sch. 1 Pt. 3 para. 3(1) substituted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(f)
- F2
Words in Sch. 1 Pt. 3 para. 3(2) substituted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(g)
- F3
Sch. 1 Pt. 3 para. 3(8) substituted (7.6.2019) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2019 (S.I. 2019/997), arts. 1, 4(1)
- F4
Words in Sch. 1 Pt. 3 para. 3(8)(a) omitted (1.10.2022) by virtue of The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022 (S.I. 2022/1015), arts. 1, 4(c)
- F5
Words in Sch. 1 Pt. 3 para. 3(8)(a) substituted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(h)
- F6
Word in Sch. 1 Pt. 3 para. 3(8)(a) substituted (1.10.2022) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022 (S.I. 2022/1015), arts. 1, 4(c)
- F7
Words in Sch. 1 Pt. 3 para. 3(8)(e) substituted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(i)
- F8
Sch. 1 Pt. 3 para. 3(9) inserted (7.6.2019) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2019 (S.I. 2019/997), arts. 1, 4(2)
Commencement
- I1
Sch. 1 Pt. 3 para. 3 in force at 29.8.2017, see art. 1