Paragraph 36 Reuse of temporary worksI1
England, Wales and Scotland
In the event that any temporary works which have been constructed pursuant to the East Anglia ONE Order are proposed to be reused by the undertaker in connection with the authorised project, such reuse may not commence until a scheme which accords with paragraph (2) has been submitted to and approved by the relevant planning authority.
The scheme to be submitted for approval under paragraph (1) must include:
details of the temporary works to be reused which must accord with the parameters for temporary works contained at requirement 12;
a timetable and details for the removal of such part of the temporary works which do not accord with the parameters for temporary works contained at requirement 12;
details of any transferee to whom the temporary works have been transferred pursuant to Article 5 of the East Anglia ONE Order as well as the date of such transfer; and
proposals to notify the relevant planning authority of any subsequent transfers pursuant to Article 5 of the East Anglia ONE Order pending reinstatement of the reused temporary works in accordance with requirement 28 of the East Anglia ONE Order.
The scheme must be implemented as approved.