Paragraph 37 Notification of site clearance and archaeological investigationsI1

England, Wales and Scotland

Notwithstanding the definition of “commence” in Article 2(1), site clearance works landward of MHWS and archaeological investigations within Work Number 67 may only be carried out by the undertaker before commencement, in circumstances where the undertaker has provided notice F1in writing to the relevant planning authority of its intention to carry out such works or investigations and

(a)

the relevant planning authority has provided a written determination that the notified works or investigations can take place; or

(b)

no response has been received by the undertaker within 15 working days of the date of notification of such works or investigations.

Annotations

Textual amendments

F1

Words in Sch. 1 Pt. 3 para. 37 substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.

Commencement

I1

Sch. 1 Pt. 3 para. 37 in force at 29.8.2017, see art. 1