Paragraph 29 Restoration of land used temporarily for constructionI1
England, Wales and Scotland
Any land landward of mean low water springs within the Order limits which is used temporarily for construction of the onshore works and not ultimately incorporated in permanent works or approved landscaping must be reinstated, in accordance with such details as the relevant planning authority in consultation with the relevant highway authority may approve, within twelve months of completion of the relevant stage of the onshore works or such other period as the relevant planning authority may approve.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 29 in force at 22.4.2022, see art. 1(2)