Paragraph 28 Control of piling and UXO detonationsI1
England, Wales and Scotland
The undertaker must not—
undertake pile driving in respect of more than one pile at the same time;
undertake more than one UXO detonation at the same time; or
undertake pile driving at the same time as undertaking a UXO detonation.
In the event that pile driving or UXO detonation is being carried out under licence 2 (transmission), the undertaker must not undertake pile driving or UXO detonation under this licence at the same time.
During the winter period the undertaker must not carry out more than one pile driving activity or UXO detonation within a 24 hour period under this licence, alone or in-combination with pile driving or UXO detonations undertaken in accordance with licence 2 (transmission).
For the purpose of this condition—
“winter period” means the period between 1st October to 31st March inclusive.
Annotations
Commencement
- I1
Sch. 13 Pt. 2 para. 28 in force at 22.4.2022, see art. 1(2)