Paragraph 21 Co-operationI1

England, Wales and Scotland

(1)

Prior to submission of plans and documentation required to be submitted to the MMO for approval in accordance with conditions 12(1), 13(1) and 22(1), the undertaker must provide a copy of the relevant plans and documentation to the East Anglia ONE North undertaker to enable the East Anglia ONE North undertaker to provide any comments on the plans and documentation to the undertaker.

(2)

The plans and documentation submitted to the MMO for approval in accordance with conditions 12(1), 13(1) and 22(1) must be accompanied by any comments received by the undertaker from the East Anglia ONE North undertaker in accordance with paragraph (1) or a statement from the undertaker confirming that no such comments were received.

(3)

The undertaker must participate in liaison meetings with the East Anglia ONE North undertaker as requested from time to time by the MMO in writing in advance, and such meetings will be chaired by the MMO and may consider such matters as are determined by the MMO relating to the efficient management and discharge of conditions 12(1), 13(1) and 22(1) of this licence and conditions 12(1), 13(1) and 22(1) of Schedule 14, Part 2 to the East Anglia ONE North Order.

(4)

For the purposes of this condition—

  • “East Anglia ONE North authorised scheme” means Work Nos. 1 to 6 of the East Anglia ONE North Order;

  • “East Anglia ONE North Order” means the East Anglia ONE North Offshore Wind Farm Order 2022; and

  • “East Anglia ONE North undertaker” means the undertaker in respect of the East Anglia ONE North authorised scheme.

Annotations

Commencement

I1

Sch. 14 Pt. 2 para. 21 in force at 22.4.2022, see art. 1(2)