Paragraph 27 Completion of constructionI1
England, Wales and Scotland
(1)
The undertaker must submit a close out report to the MMO and the relevant statutory nature conservation body confirming the date of completion of construction within three months of the date of completion of construction.
(2)
Following completion of construction, no further construction activities can be undertaken under this licence.
Annotations
Commencement
- I1
Sch. 14 Pt. 2 para. 27 in force at 22.4.2022, see art. 1(2)