Part 2 Other documents to be certifiedI1
England, Wales and Scotland
| (1) | (2) | (3) | (4) | (5) |
|---|---|---|---|---|
| Document Reference | Examination Library Reference | Document Name | Version | Date |
| 2.2 | REP11-003 | Land Plans (onshore) | 6 | Deadline 11 7th June 2021 |
| 2.2.1 | AS-002 | Land Plans (offshore) F1(Rev 2) | 1 | 20th December 2019 |
| 2.3.1 | APP-010 | Works Plans (offshore) (Rev 4) | 1 | 25th October 2019 |
| 2.3.2 | REP11-004 | Works Plans (onshore) | 7 | Deadline 11 7th June 2021 |
| 2.4 | REP12-004 | Access to Works Plan (Rev 2) | 2 | Deadline 12 28th June 2021 |
| 2.5 | REP12-005 | Temporary Stopping up of Public Rights of Way Plan (Rev 4) | 4 | Deadline 12 28th June 2021 |
| 2.6 | REP12-006 | Permanent Stopping up of Public Rights of Way Plan (Rev 4) | 3 | Deadline 12 28th June 2021 |
| 2.10 | REP12-012 | Important Hedgerows and Tree Preservation Order Plan (Rev 4) | 4 | Deadline 12 28th June 2021 |
| 2.12 | APP-022 | Order limits boundary coordinates plan (offshore) | 1 | 25th October 2019 |
| 4.3 | REP12-019 | Book of Reference (Version 10) | 10 | Deadline 12 28th June 2021 |
| 8.1 | F2. . . | Outline Code of Construction Practice (F3Version 10) | F410 | 31 January 2022 |
| 8.4 | AS-116 | Outline Public Rights of Way Strategy | 3 | 22nd April 2021 |
| 8.5 | REP6-005 | Outline Written Scheme of Investigation (Onshore Archaeology) | 3 | Deadline 6 24th February 2021 |
| 8.6 | REP3-028 | Outline Written Scheme of Investigation (Offshore) | 2 | Deadline 3 15th December 2020 |
| 8.7 | . . . | Outline Landscape and Ecological Management Strategy (Version 08) | 8 | Deadline 13 31 January 2022 |
| 8.9 | REP11-017 | Outline Construction Traffic Management Plan | 6 | Deadline 11 7th June 2021 |
| 8.10 | REP12-023 | Outline Access Management Plan (Version 07) | 7 | Deadline 12 28th June 2021 |
| 8.11 | REP11-022 | Outline Travel Plan | 6 | Deadline 11 7th June 2021 |
| 8.12 | REP7-027 | Outline Offshore Operations and Maintenance Plan | 3 | Deadline 7 4th March 2021 |
| 8.13 | REP8-027 | Offshore In Principle Monitoring Plan | 4 | Deadline 8 25th March 2021 |
| 8.14 | REP8-029 | Draft Marine Mammal Mitigation Protocol | 4 | Deadline 8 25th March 2021 |
| 8.17 | REP8-031 | In Principle East Anglia TWO Project Southern North Sea SAC Site Integrity Plan | 4 | Deadline 8 25th March 2021 |
| 8.18 | APP-595 | Outline Navigation Monitoring Strategy | 1 | 25th October 2019 |
| 8.20 | REP1-019 | Outline pre-commencement archaeology execution plan F5(onshore) | 2 | Deadline 1 2nd November 2020 |
| ExA.AS-1.D12.V4 | REP12-025 | Outline Landfall Construction Method Statement (Version 04) | 4 | Deadline 12 28th June 2021 |
| ExA.AS-2.D12.V3 | REP12-027 | Outline SPA Crossing Method Statement (Version 03) | 3 | Deadline 12 28th June 2021 |
| ExA.AS-6.D8.V2 | REP8-086 | Outline Sizewell Gap Construction Method Statement | 2 | Deadline 8 25th March 2021 |
| ExA.AS-5.D3.V2 | REP3-050 | Outline Fisheries Liaison and Coexistence Plan | 2 | Deadline 3 15th December 2020 |
| ExA.AS-4.D6.V3 | REP6-039 | Outline Sabellaria Reef Management Plan | 3 | Deadline 6 24th February 2021 |
| ExA.AS-13.D13.V7 | REP13-020 | Outline Operational Drainage Management Plan (Version 07) | 7 | Deadline 13 5th July 2021 |
| ExA.AS- 5.D12.V5 | REP12-062 | Outline Port Construction Traffic Management and Travel Plan | 5 | Deadline 12 28th June 2021 |
| ExA.AS- 29.D11.V4 | REP11-074 | Outline Watercourse Crossing Method Statement | 4 | Deadline 11 7th June 2021 |
| ExA.AS-12.D8.V3 | REP8-036 | Best Practice Protocol for Minimising Disturbance to Red-Throated Diver | 3 | Deadline 8 25th March 2021 |
| ExA.AS-6.D11.V4 | AS-133 | Substations Design Principles Statement (Rev 04) | 4 | F6... 21st June 2021 |
| ExA.AS-6.SoSQ2.V5 | . . . | Offshore Ornithology Without Prejudice Compensation Measures | 5 | 31 January 2022 |
| ExA.AS-35.D8.V2 | REP8-077 | Activity Exclusion Zones Plan | 2 | Deadline 8 25th March 2021 |
| ExA.AS-15.D7.V1 | REP7-037 | Sizewell C Order Limits Interaction – Offshore Plan | 1 | Deadline 7 4th March 2021 |
| ExA.AS-34. D9.V2 | REP9-031 | Layout Principles Statement | 2 | Deadline 9 15th April 2021 |
Annotations
Textual amendments
- F1
Words in Sch. 17 Pt. 2 inserted (22.12.2022) by The East Anglia TWO Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1399), art. 1(2), Sch.
- F2
Word in Sch. 17 Pt. 2 omitted (22.12.2022) by virtue of The East Anglia TWO Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1399), art. 1(2), Sch.
- F3
Words in Sch. 17 Pt. 2 substituted (22.12.2022) by The East Anglia TWO Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1399), art. 1(2), Sch.
- F4
Word in Sch. 17 Pt. 2 substituted (22.12.2022) by The East Anglia TWO Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1399), art. 1(2), Sch.
- F5
Word in Sch. 17 Pt. 2 inserted (22.12.2022) by The East Anglia TWO Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1399), art. 1(2), Sch.
- F6
Words in Sch. 17 Pt. 2 omitted (22.12.2022) by virtue of The East Anglia TWO Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1399), art. 1(2), Sch.
Commencement
- I1
Sch. 17 Pt. 2 in force at 22.4.2022, see art. 1(2)