OpenLegislation

Schedule 1 AUTHORISED PROJECTI1

England, Wales and Scotland

A nationally significant infrastructure project as defined in section 14(1)(p) and 30 of the 2008 Act comprising—

  • Works No.1 – A hazardous waste landfill facility for the disposal at a direct input rate of up to 150,000 tonnes per annum of hazardous waste and low level waste on the area and phases identified on the works plan (WS010001/ENRMF/PLANS/WORKS) including a landfill gas pump and gas flare, extraction and stockpiling of clay and other suitable materials for engineering purposes and the exportation of some clay and other suitable materials, all other associated engineering works to construct the landfill phases including a leachate collection system.

  • Works No.2 – A hazardous waste facility, namely the alteration of an existing soil treatment facility the details of which are as shown on the plan Elevations of the infrastructure associated with the soil treatment plant (WS010001/ENRMF/PLANS/ELEVATION5) with an increase from the currently consented capacity of F1150,000tpa to F2200,000tpa of contaminated materials comprising predominantly hazardous wastes and comprising a modular plant located on a concrete pad with associated surface water drainage and collection and adjacent stockpiles. The components of the plant include stocking areas and stocking bays with concrete A frame walls, process, reagent and water or other liquid storage tanks and silos, feed hoppers, screens, conveyors, washing units, separators, mixing vessels, sedimentation units, bioremediation area, a mobile crusher on a campaign basis, open concrete lined settlement tanks, a process control office and staff welfare facilities, bunded fuel storage tanks and an electricity generator in an insulated container.

    And in connection with such works and to the extent that they do not otherwise form part of any such work, further associated development and/or ancillary works shown on the plans referred to in the requirements including—

    1. (a)

      the continuation of the filling with hazardous waste and low level waste the existing landfill cells 4B, 5A and 5B as shown on Figure ES6 of the environmental document;

    2. (b)

      the main infrastructure and buildings including the surface water pumping station, laboratory, canteen and offices as shown on the plan Elevations of main infrastructure including buildings (WS010001/ENRMF/PLANS/ELEVATION3);

    3. (c)

      weighbridge

    4. (d)

      cess pit;

    5. (e)

      leachate storage tanks;

    6. (f)

      fuel storage tanks;

    7. (g)

      monitoring boreholes;

    8. (h)

      security cameras;

    9. (i)

      boundary fencing;

    10. (j)

      lighting;

    11. (k)

      car parking area;

    12. (l)

      internal site roads;

    13. (m)

      hardstanding and bunding;

    14. (n)

      surface water collection ponds;

    15. (o)

      surface and foul water drainage

    16. (p)

      wheel cleaning facilities

    17. (q)

      the phased restoration of the land to woodland and grassland for ecological benefit and public access pursuant to the approved scheme under requirement 5 of this Order; and

    18. (r)

      the site will be subject to a ten year aftercare and maintenance period up to 2036. During this period a leachate storage tank, the gas flare, surface water pumping station and associated fuel storage will be retained at the site.

Annotations

Textual amendments

F1

Word in Sch. 1 substituted (22.6.2018) by The East Northamptonshire Resource Management Facility (Amendment) Order 2018 (S.I. 2018/742), arts. 1, 3(a)

F2

Word in Sch. 1 substituted (22.6.2018) by The East Northamptonshire Resource Management Facility (Amendment) Order 2018 (S.I. 2018/742), arts. 1, 3(b)

Commencement

I1

Sch. 1 in force at 31.7.2013, see art. 1