The maximum quantities of F1waste that shall be imported to the soil treatment facility per annum will be 200,000 tonnes and directly to the landfill will be 150,000 tonnes. The combined total amount of waste that can be imported to the site per annum shall not exceed 250,000 tonnes. The total quantity of low level waste disposed of at the site in the period up to 31 December 2026 (or its earlier closure) shall not exceed 448,000 tonnes.

Annotations

Textual amendments

F1

Words in Sch. 2 para. 10 substituted (22.6.2018) by The East Northamptonshire Resource Management Facility (Amendment) Order 2018 (S.I. 2018/742), arts. 1, 4(a)