Work No. 3 – electrical connection works comprising—

(g)

Work No. 3A – up to 400 kilovolt underground electrical cables and control systems cables to and from the existing National Grid substation; and

(h)

Work No. 3B – works within the existing National Grid substation, including underground and over ground cables, connections to busbars and new, upgraded or replacement equipment.