Regulation 5A Investigation of smart meters not operating as intendedF1
This regulation applies where a customer notifies their supplier that the customer considers that their smart meter or in-home display is not operating as intended.
This regulation applies to all smart meters, including those operating as a prepayment meter.
Where this regulation applies, the requirements on the supplier set out in paragraph (4)(a), (b) and (c) are each an individual standard of performance.
Within 5 working days of receiving a notification under paragraph (1), the supplier must—
complete an initial assessment of whether the smart meter or in-home display is not operating as intended;
where appropriate, take action which will assist the supplier to identify the cause of the smart meter not operating as intended or to identify whether the in-home display is not operating as intended; and
offer to confirm, in writing, the nature and outcome of that initial assessment and the action taken.
In this regulation—
“customer” includes a micro-business customer, except for the purposes of paragraph (c) of the definition of “not operating as intended”; and
“not operating as intended” means operating in a manner where—
- (a)
the supplier is not receiving remote meter readings from the smart meter, either using the means provided by a smart meter communication service or otherwise;
- (b)
the customer receives an inaccurate bill as a result of the smart meter operating as described in paragraph (a);
- (c)
the in-home display is not displaying accurate real-time information about the customer’s energy consumption, including tariff or expenditure information; or
- (d)
in the case of a smart meter intended to operate as a prepayment meter, the customer is unable to pay remotely in advance for the consumption of gas or electricity through that meter.
- (a)
Annotations
Textual amendments
- F1
Reg. 5A inserted (23.2.2026) by The Electricity and Gas (Standards of Performance) (Suppliers) (Amendment) Regulations 2026 (S.I. 2026/73), regs. 1(1), 5