Article 5 Conditions on exemptions
The exemption granted by article 3(b) of this Order is subject to compliance with the following conditions—
(a)
Ferrybridge Multifuel 2 Generating Station is connected to the total system in England and Wales;
(b)
Ferrybridge Multifuel 2 Generating Station does not export more than 100 megawatts of electrical power to the total system in England and Wales, except in circumstances outside the reasonable control of Ferrybridge MFE 2 Limited; and
(c)
Ferrybridge MFE 2 Limited is not a licensed generator.