OpenLegislation

Division 7.2.2 IMPLEMENTATION: INFRASTRUCTURE (STATIONARY EQUIPMENT)

United Kingdom

Original text. Later amendments are not shown.

The following requirements apply to the three categories of line defined in Article 5c of the Directive:

  • lines specially built for high speed,

  • lines specially upgraded for high speed,

  • lines specially upgraded for high speed which have special features as a result of topographical, relief or town-planning constraints.

The following cases in points 7.2.2.1, 7.2.2.2 and 7.2.2.3 (according to Article 1 of the Directive) apply to the abovementioned categories.

  1. 7.2.2.1Lines to be constructed
  2. 7.2.2.2Lines to be upgraded (re-signalled)
  3. 7.2.2.3Existing lines
  4. 7.2.2.4Registers of infrastructure (TEN HS)