After the conclusion of the contract with the manufacturer, the responsible TAB must inform the Secretary of State of the work programme for drawing up the UK Assessment Document and the schedule for its execution and indicate the assessment programme. This communication must take place within 3 months of receipt of the request for a UK Technical Assessment.

Annotations

Textual amendments

F1

Annex 2 substituted (31.12.2020) by The Construction Products (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/465), reg. 1, Sch. 1 para. 66 (with Sch. 1 para. 70) (as amended by S.I. 2020/1359, reg. 1, Sch. 1 paras. 12, 17); 2020 c. 1, Sch. 5 para. 1(1)