Division 4.4.2.1.3 The phase-specific pure electric-range PERp for PEVs shall be calculated from the Type 1 test as described in paragraph 3.4.4.2. of this Sub-Annex by using the following equations:

Original text. Later amendments are not shown.

PERp=UBESTPECDC,p

where:

F1UBESTP
  • is the usable REESS energy in accordance with paragraph 4.4.2.1.1. of this Sub-Annex, Wh;

  • ECDC,p
  • is the weighted electric energy consumption for each individual phase of DS1 and DS2 of the shortened Type 1 test procedure, Wh/km;

  • In the case that phase p = low and phase p = medium, the following equations shall be used:

    ECDC,p=∑j= 14 ECDC,p,j× Kp,j

    where:

    ECDC,p,j
  • is the electric energy consumption for phase p where the first phase p of DS1 is indicated as j = 1, the second phase p of DS1 is indicated as j = 2, the first phase p of DS2 is indicated as j = 3 and the second phase p of DS2 is indicated as j = 4 of the shortened Type 1 test procedure according to paragraph 4.3. of this Sub-Annex, Wh/km;

  • Kp,j
  • is the weighting factor for phase p where the first phase p of DS1 is indicated as j = 1, the second phase p of DS1 is indicated as j = 2, the first phase p of DS2 is indicated as j = 3, and the second phase p of DS2 is indicated as j = 4 of the shortened Type 1 test procedure;

  • and

    Kp,1=ΔEREESS,p,1UBESTPand Kp,j=1− Kp,13 for j= 2 ... 4

    where:

    ΔEREESS,p,1
  • is the energy change of all REESSs during the first phase p of DS1 of the shortened Type 1 test procedure, Wh.

  • In the case that phase p = high and phase p = extraHigh, the following equations shall be used:

    ECDC,p=∑j= 12 ECDC,p,j× Kp,j

    where:

    ECDC,p,j
  • is the electric energy consumption for phase p of DSj of the shortened Type 1 test procedure according to paragraph 4.3. of this Sub-Annex, Wh/km;

  • kp,j
  • is the weighting factor for phase p of DSj of the shortened Type 1 test procedure

  • and

    Kp,1=ΔEREESS,p,1UBESTP and Kp,2= 1− Kp,1

    where:

    ΔEREESS,p,1
  • is the electric energy change of all REESSs during the first phase p of DS1 of the shortened Type 1 test procedure, Wh.

  • Annotations

    Textual amendments

    F1

    Substituted by Commission Regulation (EU) 2018/1832 of 5 November 2018 amending Directive 2007/46/EC of the European Parliament and of the Council, Commission Regulation (EC) No 692/2008 and Commission Regulation (EU) 2017/1151 for the purpose of improving the emission type approval tests and procedures for light passenger and commercial vehicles, including those for in-service conformity and real-driving emissions and introducing devices for monitoring the consumption of fuel and electric energy (Text with EEA relevance).