Article 101 Management of the ‘testing’ status of relevant assets
United Kingdom
The outage planning agent of a relevant asset the availability status of which has been declared as ‘testing’ shall provide the TSO, and, if connected to a distribution system, including closed distribution systems, the DSO or the CDSO within 1 month before the start of the ‘testing’ status, with:
a detailed test plan;
an indicative generation or consumption schedule if the concerned relevant asset is a relevant power generating module or a relevant demand facility; and
changes to the topology of the transmission system or distribution system if the concerned relevant asset is a relevant grid element.
The outage planning agent shall update the information referred to in paragraph 1 as soon as it is subject to any change.
The TSO of a relevant asset the availability status of which has been declared as ‘testing’ shall provide the information received in accordance with paragraph 1 to all other TSOs F1..., upon their request.
Where the relevant asset referred to in paragraph 1 is a relevant grid element interconnecting two or more control areas, the TSOs of the concerned control areas shall agree on the information to be provided pursuant to paragraph 1.
Annotations
Textual amendments
- F1
Words in Art. 101(3) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 67 (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)