Article 52 Data exchange between TSOs and transmission-connected demand facilities
United Kingdom
Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following structural data to the TSO:
electrical data of the transformers connected to the transmission system;
characteristics of the load of the demand facility; and
characteristics of the reactive power control.
Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO:
scheduled active and forecasted reactive power consumption on a day-ahead and intraday basis, including any changes of those schedules or forecast;
any forecasted restriction in the reactive power control capability;
in case of participation in demand response, a schedule of its structural minimum and maximum power range to be curtailed F1...
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO in real-time:
active and reactive power at the connection point; and
the minimum and maximum power range to be curtailed.
Each transmission-connected demand facility owner shall describe to its TSO its behaviour at the voltage ranges referred to in Article 27.
Annotations
Textual amendments
- F1
Art. 52(2)(d) and word omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 43 (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)