Article 12 Dispatching of generation and demand response

United Kingdom

Original text. Later amendments are not shown.

1.

The dispatching of power-generating facilities and demand response shall be non-discriminatory, transparent and, unless otherwise provided under paragraphs 2 to 6, market based.

2.

F1... F2the regulatory authority shall ensure that when dispatching electricity generating installations, system operators shall give priority to generating installations using renewable energy sources to the extent permitted by the secure operation of the national electricity system, based on transparent and non-discriminatory criteria and where such power-generating facilities are either:

(a)

power-generating facilities that use renewable energy sources and have an installed electricity capacity of less than 400 kW; or

(b)

demonstration projects for innovative technologies, subject to approval by the regulatory authority, provided that such priority is limited to the time and extent necessary for achieving the demonstration purposes.

3.

F3The regulatory authority may decide not to apply priority dispatch to power-generating facilities as referred to in point (a) of paragraph 2 with a start of operation at least six months after that decision, or to apply a lower minimum capacity than that set out under point (a) of paragraph 2, provided that:

(a)

it has well-functioning intraday and other wholesale and balancing markets and that those markets are fully accessible to all market participants in accordance with this Regulation;

(b)

redispatching rules and congestion management are transparent to all market participants;

F4(c)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(d)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(e)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Any derogation shall avoid retroactive changes that affect generating installations already benefiting from priority dispatch, notwithstanding any agreement between F5the regulatory authority and the operator of a generating installation on a voluntary basis.

F6... F7the regulatory authority may provide incentives to installations eligible for priority dispatch to voluntarily give up priority dispatch.

4.

F8... F9the regulatory authority may provide for priority dispatch for electricity generated in power-generating facilities using high-efficiency cogeneration with an installed electricity capacity of less than 400 kW.

5.

For power-generating facilities commissioned as from 1 January 2026, point (a) of paragraph 2 shall apply only to power-generating facilities that use renewable energy sources and have an installed electricity capacity of less than 200 kW.

6.

Without prejudice to contracts concluded before 4 July 2019, power-generating facilities that use renewable energy sources or high-efficiency cogeneration and were commissioned before 4 July 2019 and, when commissioned, were subject to priority dispatch under Article 15(5) of Directive 2012/27/EU or Article 16(2) of Directive 2009/28/EC of the European Parliament and of the Councilf1 shall continue to benefit from priority dispatch. Priority dispatch shall no longer apply to such power-generating facilities from the date on which the power-generating facility becomes subject to significant modifications, which shall be deemed to be the case at least where a new connection agreement is required or where the generation capacity of the power-generating facility is increased.

7.

Priority dispatch shall not endanger the secure operation of the electricity system F10....

Annotations

Textual amendments

F1

Words in Art. 12(2) omitted (31.12.2020) by virtue of The State Aid (Revocations and Amendments) (EU Exit) Regulations 2020 (S.I. 2020/1470), reg. 1(2), Sch. 1 para. 10(3)(a) (with Sch. 3)

F2

Words in Art. 12(2) substituted (E.W.S.) (31.12.2020) by The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1006), reg. 1(2), Sch. 4 para. 12(2)

F3

Words in Art. 12(3) substituted (E.W.S.) (31.12.2020) by The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1006), reg. 1(2), Sch. 4 para. 12(3)(a)

F4

Art. 12(3)(c)-(e) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1006), reg. 1(2), Sch. 4 para. 12(3)(b)

F5

Words in Art. 12(3) substituted (E.W.S.) (31.12.2020) by The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1006), reg. 1(2), Sch. 4 para. 12(3)(c)

F6

Words in Art. 12(3) omitted (31.12.2020) by virtue of The State Aid (Revocations and Amendments) (EU Exit) Regulations 2020 (S.I. 2020/1470), reg. 1(2), Sch. 1 para. 10(3)(b) (with Sch. 3)

F7

Words in Art. 12(3) substituted (E.W.S.) (31.12.2020) by The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1006), reg. 1(2), Sch. 4 para. 12(3)(d)

F8

Words in Art. 12(4) omitted (31.12.2020) by virtue of The State Aid (Revocations and Amendments) (EU Exit) Regulations 2020 (S.I. 2020/1470), reg. 1(2), Sch. 1 para. 10(3)(c) (with Sch. 3)

F9

Words in Art. 12(4) substituted (E.W.S.) (31.12.2020) by The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1006), reg. 1(2), Sch. 4 para. 12(4)

F10

Words in Art. 12(7) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1006), reg. 1(2), Sch. 4 para. 12(5)

Footnotes

f1

Directive 2009/28/EC of the European Parliament and of the Council of 23 April 2009 on the promotion of the use of energy from renewable sources and amending and subsequently repealing Directives 2001/77/EC and 2003/30/EC (OJ L 140, 5.6.2009, p. 16).