Paragraph 35 I1

The undertaker must submit a close out report to the MCA and the UK Hydrographic Office within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following—

(a)

the final number of installed wind turbine generators;

(b)

a plan of the layout of installed wind turbine generators and offshore platform; and

(c)

latitude and longitude coordinates of the centre point of the location of each wind turbine generator and offshore platform, provided as Geographical Information System data referenced to WGS84 datum.