OpenLegislation

Paragraph 36 Reporting of scour and cable protection;I1

England and Wales

(1)

Not more than four months following completion of the construction of the authorised development, the undertaker must provide the MMO and the relevant statutory nature conservation bodies with a report setting out details of the cable protection and scour protection used for the authorised development.

(2)

The report must include the following information—

(a)

the location of cable protection and scour protection;

(b)

the volume of cable protection and scour protection; and

(c)

any other information relating to the cable protection and scour protection as agreed between the MMO and the undertaker.

Annotations

Commencement

I1

Sch. 10 para. 36 in force at 8.1.2026, see art. 1