Paragraph 34 Stages of constructionI1

England and Wales

(1)

The licenced activities must not be commenced until a written scheme setting out the stages of construction of the authorised development seaward of MHWS has been submitted to and approved by the MMO in writing.

(2)

The scheme must be implemented as approved.

(3)

The written scheme referred to in sub-paragraph (1) must be submitted to the MMO in writing four months prior to the planned commencement of the licenced activities.

Annotations

Commencement

I1

Sch. 11 para. 34 in force at 8.1.2026, see art. 1