OpenLegislation

Paragraph 35 Completion of constructionI1

England and Wales

(1)

The undertaker must submit a close out report in writing to the MMO and the relevant statutory nature conservation body within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the final number of installed offshore electrical installations.

(2)

Following completion of construction, no further construction activities can be undertaken under this licence.

Annotations

Commencement

I1

Sch. 11 para. 35 in force at 8.1.2026, see art. 1