Paragraph 13 Ground water monitoringI1
England and Wales
(1)
No stage of the onshore works for which a groundwater monitoring plan is required in accordance with the outline groundwater monitoring plan, must be commenced until, for that stage a groundwater monitoring plan has been submitted to and approved by the discharging authority.
(2)
Sub-paragraph (1) does not apply to any works or surveying and investigation necessary to inform the preparation of a groundwater monitoring plan.
(3)
Any plan approved under sub-paragraph (1) must be implemented as approved.
Annotations
Commencement
- I1
Sch. 2 Pt. 1 para. 13 in force at 8.1.2026, see art. 1