Paragraph 13 Ground water monitoringI1

England and Wales As made

(1)

No stage of the onshore works for which a groundwater monitoring plan is required in accordance with the outline groundwater monitoring plan, must be commenced until, for that stage a groundwater monitoring plan has been submitted to and approved by the discharging authority.

(2)

Sub-paragraph (1) does not apply to any works or surveying and investigation necessary to inform the preparation of a groundwater monitoring plan.

(3)

Any plan approved under sub-paragraph (1) must be implemented as approved.