No development of any new or diverted public right of way listed in Part 3 of Schedule 4 (footways and cycle tracks) may be carried out until a public rights of way implementation plan for that public right of way has been submitted to and approved by the relevant highway authority.

(2)

Each public rights of way implementation plan submitted pursuant to sub-paragraph (1) must be substantially in accordance with the public rights of way management strategy and in accordance with the rights of way and access plans.

(3)

The development of any new or diverted public right of way listed in Part 3 of Schedule 4 must be carried out in accordance with the relevant public rights of way implementation plan approved pursuant to sub-paragraph (1) unless otherwise agreed in writing with the relevant highway authority.

Annotations

Commencement

I1

Sch. 2 para. 22 in force at 12.10.2025, see art. 1